People often ask how long their bathroom will be out of service. The honest answer has two parts: the time before demolition, when the room is still usable and the project is being designed and ordered, and the time on site, when the room is closed. We plan the first part carefully so the second part runs without stalls.
Phase 1: Design visit and layout (1 to 2 weeks)
We visit, measure and talk through goals. Within about a week, you have a plan drawing and a detailed price in hand. Revisions happen here, on paper.
Phase 2: Selections and ordering (1 to 4 weeks)
You choose tile, the vanity and top, fixtures, lighting and glass style. We order everything before demolition so the job does not stall waiting for a missing faucet. Custom vanities and some tile can take several weeks to arrive.
Phase 3: Permits (days to a few weeks)
If the project needs plumbing, electrical or building permits, we apply during ordering. Simple trade permits are often issued quickly; larger projects with plan review take longer.
Phase 4: Demolition (1 to 3 days)
We protect the floors and the path to the bathroom, put up dust barriers and remove tile, fixtures, the tub or shower, the vanity and any damaged drywall or subfloor. Hidden issues such as old leaks, rotted framing or failed shower pans show up here, and we photograph and price any extra repairs before doing them.

Phase 5: Slab, plumbing and electrical rough-in (2 to 7 days)
If drains move, the slab is saw-cut, trenched and re-poured; post-tensioned slabs take extra care to avoid the tendons. Licensed plumbers set drains and supply lines and licensed electricians run new circuits. Rough-in inspections happen before anything is covered.
Phase 6: Framing, waterproofing and flood test (3 to 6 days)
We frame niches, benches and blocking, install backer board, apply the bonded waterproof membrane and flood-test the shower pan before tile.
Phase 7: Tile (4 to 10 days)
Tile setting is the longest hands-on phase. Large-format tile, patterns and full-height showers take longer. Grout and sealant follow once the thinset has cured.
Phase 8: Vanity, fixtures, paint and trim (3 to 5 days)
The vanity and top go in, followed by the toilet, faucets, shower trim, lighting, mirrors and accessories. Walls are painted and trim installed.
Phase 9: Glass (1 to 2 weeks after tile)
Frameless glass is measured after tile and fabricated to fit, usually in one to two weeks. In the meantime, the shower can often be used with a temporary curtain.
Phase 10: Final inspections and walk-through
Final inspections for any permits, a thorough cleaning and a walk-through with you, checking every fixture, drawer and caulk line.
Typical totals
| Project | On-site time |
|---|---|
| Powder room | 1 to 2 weeks |
| Hall bath, same layout | 2 to 4 weeks |
| Hall bath tub-to-shower | 1 to 3 weeks |
| Primary bath with layout changes | 4 to 7 weeks |
| Luxury primary suite | 6 to 9 weeks |
What slows down a Plano bathroom schedule
Late selections. The most common delay is a decision still open when demolition starts, such as a vanity, a valve or the glass hardware. We finish selections first for this reason.
Supply lead times. Semi-custom cabinetry can take four to eight weeks, special-order tile two to six weeks, and some valves and trim kits a few weeks. Ordering early removes most of that risk.
Hidden damage. Rot under a shower pan, a cracked drain or old supply lines can add a few days once discovered.
Inspection scheduling. City inspections are usually scheduled quickly, but busy periods can add a day or two between stages.
Holidays and weather. Deliveries slow around Thanksgiving and the winter holidays. Interior bathroom work is rarely affected by weather, though severe storms can delay material drops.
Living through a bathroom remodel
During demolition, expect noise and some dust, especially with old mortar beds or tile. During rough-in and waterproofing, the work is quieter and the bathroom is closed off. Tile days involve wet saws, which we run outside or in a garage when possible. In the final stage, cabinets, fixtures and paint go in, and the room starts to look finished. Most homeowners say the second week feels the slowest and the last week feels the fastest.
An example hall bath calendar
For a typical Plano hall bath tub-to-shower conversion, after design and ordering are complete, a schedule might look like this, offered as an illustration:
- Days 1 to 2: Protection, demolition and haul-off.
- Days 3 to 5: Plumbing rough-in for the new valve and drain, slab work if needed, and inspection.
- Days 6 to 8: Framing touch-ups, backer board, waterproofing and a 24-hour flood test.
- Days 9 to 13: Wall and floor tile, then grout.
- Days 14 to 16: Vanity, top, toilet, fixtures, paint and trim.
- About one to two weeks later: Frameless glass installation and final walk-through.
Before construction: the planning weeks
The weeks before demolition matter as much as the build. During this time we finalize the layout, confirm every selection, order materials, submit permits and set a start date. Homeowners who settle choices quickly usually see the shortest overall timeline. A good rule of thumb is to allow four to eight weeks from the first design visit to the first day of demolition for most bathrooms.
Timelines by bathroom type
- Powder room: about one week on site.
- Hall bath, same layout: about two to three weeks on site.
- Tub-to-shower conversion: about two to four weeks on site, plus glass.
- Primary suite: about four to seven weeks on site.
- Luxury suite with steam or stone slabs: six to nine weeks or more.
How we keep you updated during the build
We give you a written schedule before work starts and update it as phases finish. You get photos at key stages, a heads-up the day before inspections or deliveries and a quick message if anything changes. If you are traveling or working, you can follow the progress without being on site.
Coordinating the remodel with other home projects
If you are also painting, replacing flooring in the adjoining bedroom or updating the water heater, tell us early. We can sequence the bathroom so it does not conflict with other work, and sometimes combine efforts to save time.